This project consisted
of the phase 1; "Swim & Tennis facility" and the new
phase 2; "Country Club building." Both the Swim & Tennis
and the Country Club facilities have painted trim in a multitude of
colors and exotic wallcoverings. One large area at the Country Club
incorporated some complex painted "Faux finishes" on the
walls, millwork and trim. The exterior of the building has painted
wood trim and the bodies of the buildings are finished off with painted
brick and siding. Due to a compressed schedule, the project required
us to "accelerate" a typical schedule greatly. We responded
with doubled crew sizes and extra hours to help get the project done
on time.