AG Rhodes
Built by Hardin Construction, this 115 bed assisted living facility required 8 painters and 2 paperhangers 10 weeks to complete the finishes.
Chancellor Park
Built by Suffolk Construction, this 220 bed assisted living facility required 15 painters and 2 paperhangers 12 weeks to complete the finishes.

SFI Management Team
Project Manager: Gary White
Field Superintendent:  Jim Havens
Jobsite Foreman:  Tim Wall
Category: Assisted Living